Liwa Strategic Water Storage and Recovery System

By Subhi Kussad,

The objective of the project is to infiltrate and store 27 million cubic metres of desalinated water in natural underground aquifers to form a strategic reserve that can be recovered and used in emergency conditions.

ACC’s role in the project included design, supply, construction and commissioning of 200 water wells, 160 km of interconnecting piping and transfer pipeline (48″ and 36″ diameter), five pumping stations, MV and LV substations, 500 km of electrical and instrumentation cables with DCS and SCADA control systems.

 

  Category:
  Comments: Comments Off on Liwa Strategic Water Storage and Recovery System

Fujairah F1 Reverse Osmosis Plant Extension

By ,

The Project comprises the detailed design, procurement and construction of Civil & Structural works of Reverse Osmosis Extension Plant facilities on unused land that forms part of the existing F1 Plant. The scope also covers laying the GRP pipeline, including steel supports installation.

 

 

  Category:
  Comments: Comments Off on Fujairah F1 Reverse Osmosis Plant Extension

Central Environmental Protection Facility Beaat 2

By ,

Our scope of work for this project included site preparation, design, construction and supply of civil, structural and architectural works.

It also involved supply, installation and testing of piping systems, assembly and installation of mechanical equipment, supply and installation of tank works & equipment and piping insulation.

  Category:
  Comments: Comments Off on Central Environmental Protection Facility Beaat 2

Mussafah Pumping Station

By Subhi Kussad,

The project consisted of 6 water tanks, a pumping station building, a switchgear building, a chlorination building and all other relevant infrastructures and facilities (underground piping, truss blocks, roads, cable trenches, concrete fence and security building).

  Category:
  Comments: Comments Off on Mussafah Pumping Station